Rangers Factory
Sunlit future in partnership with EcoSoch Solar has installed a 391 kW on-grid Solar PV system on one of the apparel factories in Bangalore. Usually, On-Grid systems stop generating electricity when there are power cuts. This factory has diesel generators as back up. During power cuts, the diesel generators produce a reference voltage and frequency, matching the grid, to the solar inverters. Once the inverters are switched on, the load is supplied by both the solar panels and the diesel generators, running at a low RPM. This reduces the diesel usually needed to run the factory when the grid isn’t available. This is the first of its kind solar system in Karnataka state.
CAPACITY | 391 kW |
TYPE OF ROOF | Corrugated and flat |
NUMBER OF PANELS | 1242 |
ORIENTATION | North-south |
TYPE OF PANELS | Poly-crystalline |
PANEL WATTAGE | 315 W |
NO. OF INVERTERS | 13 |
INVERTER CAPACITY | 25 kW Schneider |
AVERAGE UNITS PER DAY | 1560 |
AVERAGE UNITS PER YEAR | 569 400 |
DATE OF COMMISSION | July, 2016 |